Traffic alert, April 21, 2013

Road closures and maintenance projects may affect traffic this week:

Interstate 70 Business Reconstruction Phase 3: From 25 Road east to about 1,000 feet east of the Rimrock Avenue intersection.

Project involves full concrete reconstruction, the addition of a third lane in each direction and access and intersection improvements.

Two lanes in each direction will be kept open, short traffic stops may occur and will be kept to a minimum.

The speed limit in the project area will be reduced from 45 mph to 35 mph.

Left turns in the project area can be made only at the signalized intersections.

All business access will be maintained, but may be altered at times.

Some evening and weekend work will be done as necessary to expedite the project.

22 Road Realignment Project: Reconstruction of one-third of a mile of U.S. Highway 6 between Valley Court and the Exit 26 Interchange.

The new intersection will move 500 feet west of its existing location to improve safety and efficiency. A new connecting street will be built linking Valley Court to 22 Road.

The first work involves removing the existing median and putting down temporary paving.

There will be lane shifts in the work area during the day time. Traffic will move to the outside edges of the road, but two lanes of traffic will be maintained in either direction.

Speed limits in the work zone will be reduced to 35 mph.

Grand Avenue asphalt patching: On Monday, Grand Avenue will be closed starting at 7 p.m. between Fifth Street and Seventh Street to patch the asphalt.

The work will take about four to six hours, and Grand Avenue will reopen afterward.

2013 Street Overlay Program:

Paving will take place on Noland Avenue and First Avenue on Monday.

Reconstruction will take place on Spruce Street starting Monday, and continuing through Friday.

Paving will take place on 28 1/4 Road on Tuesday and Wednesday.

Paving on Bunting is planned for Thursday.

Paving will take place on 15th Street on Friday, April 26, and Monday, April 29

All dates are subject to change depending on the weather.


COMMENTS

Commenting is not available in this channel entry.


TOP JOBS
Search More Jobs





THE DAILY SENTINEL
734 S. Seventh St.
Grand Junction, CO 81501
970-242-5050
Editions
Subscribe to print edition
E-edition
Advertisers
Advertiser Tearsheet
Information

© 2015 Grand Junction Media, Inc.
By using this site you agree to the Visitor Agreement and the Privacy Policy